10. Recommendation to: (1) award a bid and approve the Agreement to the lowest responsive, responsible bidder for the Future of Work 230 Edison Facility Remodel Project, PWP-WA-2025-026 [staff recommends Houston Smith Construction, Inc., in the amount of $1,433,918.87]; and (2) approve a project contingency fund in the amount of $75,000.00, for a total project cost not to exceed $1,508,918.87. This capital project will remodel the office area at 230 Edison, Reno with new finishes and infrastructure in preparation for new systems furniture installation. Community Services. (Commission District 2.) FOR POSSIBLE ACTION